Procedure For Running 30” Conductor

Preparation, planning and procedure for running 30" conductor.

Job Preparation

Note: Well must be drilled to depth.  Plan on top 30” conductor pipe being 1.285m down from top of cellar.  Do…

Mandrel Casing Hangers

This article describes the mandrel casing hanger make-up and running proedures.

Mandrel Casing Hanger Make-up

The “total” hanger will consist of:

  • bottom pupjoint
  • MCH (Mandrel Casing Hanger)
  • top…

Loadout List for Casing Operations

Loadout lists for 30", 20", 13 3/8", 9 5/8", 7" casing operations

Loadout list, Equipment list for 30" conductor casing operations

13.3/8 " Casing Running Programme

1. Voor running casing een veiligheids meeting waarbij alle

betrokkenen aanwezig zijn. Vermeldt in Dagelijks rapport.

R/U om casing te runnen.

2. Make up & pipelock shoetrack volgens de running…