Well Control - Bullheading

Print

Bullheading. If normal well killing techniques with conventional circulation are not possible or will result in critical well control conditions, bullheading may be considered. Mud/influx are displaced/squeezed back downhole into the weakest exposed open hole formation.

Bullheading may be considered when the following well control situations occur:

  • H2S influx cannot be handled safely by rig personnel and equipment.
  • A combined kick and losses situation is experienced (downhole annulus bullhead rates must exceed the gas migration rate to ensure the situation does not deteriorate further).
  • Kick calculations show that MAASP will be largely exceeded and probably results in a detrimental well control situation when the well is killed conventionally. In this case, only the influx needs to be squeezed back.

Bullheading is not a routine well control method. In many cases it will be doubtful whether the well can be killed by squeezing back the influx into the formation. A permanent loss situation may be created by pumping fluid immediately below the shoe. Each case must be judged on its own merits, considering such variables as:

  • Formation permeability

The formation must have good permeability/porosity to allow squeezing. The actual kick can be used as an indicator (inflow performance prior to closing in the well and the speed of pressure build-up after the well is closed-in).

  • Type of influx

A gas is easier to squeeze back than a liquid. Also, the higher the viscosity of a liquid, the more difficult it is to squeeze.

  • Contamination of influx with mud

If the influx is contaminated with mud (which will be the case with most kicks), squeezing will be much more difficult, because of the plastering qualities of the mud and the possible presence of cuttings.

  • Position of influx

If the influx has migrated, or has been circulated up over a certain distance, mud below the influx will have to be squeezed ahead of the influx, assuming that the weakest formation is where the influx came from.

  • Strength of the formation

Squeezing should be performed with the aim not to fracture any formation. In principle, the surface squeeze pressure should not exceed the pre-calculated MAASP. If heavier kill mud is pumped down the annulus, MAASP should be adjusted accordingly.

  • Casing burst strength at surface and wellhead/BOP pressure rating

The casing burst strength should always be taken into account when bullheading is considered. An appropriate safety factor should be selected which depends on the condition of the casing and possible casing wear.

Bullheading has the following disadvantages:

  • small chance of successfully squeezing the influx back into the formation;
  • fluid will go to the weakest formation which may not be the formation where the influx came from;
  • there is a potential risk of fracturing formation anywhere along the open hole section which can lead to an (internal) blowout situation. In the case of shallow casing setting depths this could lead to cratering;
  • high pressures may have to be applied to surface/subsurface equipment.

Even if squeezing fluid back into the formation is possible to some extent, it may not be possible to kill the well completely. Different well control techniques may then have to be employed.

It is obvious that, the earlier bullheading is being implemented, the better the chances of success. Bullheading is not a routine operation and competent authorities need to be consulted prior to implementing this well control method.

Bullheading is an acceptable method in killing completed gas wells (i.e. actual producing wells or production tested cased exploration wells).

Operational considerations for bullheading include the following:

  • When high pressures need to be applied, the cementing unit should be used for better control and adequate pressure rating.
  • Large mud volumes and LCM pills should be available in case major losses are experienced during bullheading.
  • A kill line connection above the bottom pipe rams of the BOP stack should be used to be able to isolate the annulus in case of a kill line failure.
  • A check valve should be installed in the kill line.

Comments  

#2 drillingdoctor 2014-04-15 11:43
You bullhead with the same type of mud you used to drill the formation.
Quote
#1 osuji lasbery 2014-03-15 17:17
Do we bullhead with diesel or fresh water.if both, how do we when to bullhead with any of them.
Do you train personnel in nigeria? What are your training packages
Quote

Additional information